PPP Process

PPP Process

Estimated Timetable

Date Milestone
June 19, 2017 Invitation for Bids / Issuance of Instructions to Bidders and Draft Bidding Documents
September 4, 2017 Deadline for First Round of bidder questions/clarifications
September 26-28, 2017 Bidders’ Conference and Airport Site Visit
October 17, 2017 Deadline for bidder mark up of bid documents
January 29, 2018 Issuance of revised draft Concession Agreement
February 15-16, 2018 Follow-up one-on-one discussions with Bidders
March 21, 2018 Deadline to submit a Bidder composition change proposal to the GOJ as per Clauses 4.1.2 and 4.1.3 of the Request for Qualification
April 18, 2018 Issuance of the final bid documents
May 30, 2018 Bid Submission Deadline
May 30, 2018 Bids Opening
June 2018 Evaluation of Bids and selection of Provisional Preferred Bidder
July 2018 Execution of the Concession Agreement with the Concessionaire
July 2019 Financial closing