Estimated Timetable

Date Milestone
February 20, 2017 Issuance of the Request for Qualification
March 20, 2017 Prospective Bidder clarifications submission deadline
March 27, 2017 Responses to Prospective Bidder clarifications
May 1, 2017 Prequalification Application Submission Deadline
June 19, 2017 Announcement of Prequalified Bidders
June 19, 2017 Issuance of the Request for Proposal - including draft Concession Agreement and opening of virtual data room
September 4, 2017 Deadline for First Round of bidder questions/clarifications
September 26-27, 2017 Bidder's conference and Site Visit in Jamaica
October 2, 2017 Deadline for bidder mark up of bid documents
December 4, 2017 Issuance of the final bid documents
January 15, 2018 Bid submission deadline
February 2018 Evaluation of Bids and selection of Provisional Preferred Bidder
March - April 2018 Execution of the Concession Agreement with the Concessionaire
December 2018 Financial closing